Provisional Sums Are Where Profit Margins Disappear.

Mixed-use commercial building, 6 floors. Noticed variation claims were escalating rapidly. Root cause: provisional sums for electromechanical works and finishes were significantly underestimated at design stage by the client's QS. Supplier proformas validated the contractor's entitlements.

Case Study — Commercial Developer — Caribbean hero visual

The Challenge

What Was Happening on the Ground

Mixed-use commercial building, 6 floors. Noticed variation claims were escalating rapidly. Root cause: provisional sums for electromechanical works and finishes were significantly underestimated at design stage by the client's QS. Supplier proformas validated the contractor's entitlements.

Case Study — Commercial Developer — Caribbean challenge visual

Before & After

The Before and After

MetricBeforeAfter

Systems Implemented

Systems We Put in Place

1

System

Variation register with entitlement audit

2

System

EM scope reconciliation against drawings

3

System

Provisional sum true-up analysis

4

System

Monthly cost report to client/lender

5

System

Remaining works scope lock protocol

6

System

Final account negotiation strategy

Outcomes

What Changed

$310K in variation claims reduced or rejected through entitlement challenges

Client had a credible final account forecast

Scope locked for remaining EM and finishes works - variation exposure capped

Client-side QS brief strengthened for future projects to prevent recurrence